ROAD CONTRUCTION UPDATES

2026

Merryall Rd (Papermill to W. Meetinghouse): drainage work in progress

Hine Hill Rd Mill and Pave (Grove St to Sunrise): milled and paved, curbing and backfill to be completed 10/22

River Rd: drainage work completed, paving scheduled for week of 11/2

Jerusalem Rd: COMPLETED

Sunrise Lane: COMPLETED

Candlewood Mtn Rd: COMPLETED

Sand Rd: COMPLETED

Cornwall Dr & Adams Ln: COMPLETED

PLEASE USE CAUTION OR SEEK ALTERNATE ROUTES DURING CONTRUCTION!

Current Schedule: